title: "What is an FTE-month? · DeliverySheet"
description: "An FTE-month is one full-time person working for one month: a coarse capacity unit that sums across teams and converts to cost in one multiplication."
canonical_url: "https://www.deliverysheet.com/glossary/fte-month"
meta:
  author: "Tan Gravam"
  "og:description": "An FTE-month is one full-time person working for one month: a coarse capacity unit that sums across teams and converts to cost in one multiplication."
  "og:image": "https://www.deliverysheet.com/_og/s/o_793efb74bb021983.png"
  "og:image:alt": "FTE-month — DeliverySheet glossary card"
  "og:image:height": "600"
  "og:image:type": image/png
  "og:image:width": "1200"
  "og:title": "What is an FTE-month? — DeliverySheet glossary"
  "twitter:description": "An FTE-month is one full-time person working for one month: a coarse capacity unit that sums across teams and converts to cost in one multiplication."
  "twitter:image": "https://www.deliverysheet.com/_og/s/o_793efb74bb021983.png"
  "twitter:image:alt": "FTE-month — DeliverySheet glossary card"
  "twitter:title": "What is an FTE-month? — DeliverySheet glossary"
---

> Index of every page on this site: [llms.txt](https://www.deliverysheet.com/llms.txt)

[← All terms](https://www.deliverysheet.com/glossary)

**Glossary **

# **What is an FTE-month?**

An FTE-month is one full-time person working for one month — a capacity unit that is comparable across teams and, where cost is recorded, is the multiplier a cost forecast would use.

Unlike story points, which are deliberately team-local and have no monetary meaning, FTE-months can be summed across teams and multiplied by a monthly cost. They are coarse on purpose: the granularity broadcasts its own error bar.

## **How to calculate FTE-months**

Gross capacity first: headcount multiplied by the months in the period. A team of six over a quarter has 6 × 3 = 18 FTE-months. Then subtract what is already spoken for — the support rotation, run-the-business work, booked holidays, the standing meeting load — and an interruption reserve if you have no data yet (twenty per cent is a defensible opening claim). What remains is the honest line: the capacity that can actually be promised.

Sizing a demand works in the same unit: two people for two months is 4 FTE-months, whichever two people it turns out to be. One decimal place at most — an FTE-month estimate with two significant figures is claiming a precision the unit deliberately does not have.

## **When to use FTE-months — and when not to**

Use them at the altitude where a promise is being made to someone outside the team: commitment decisions, quarter plans, budget conversations. That is where the unit's three properties pay: it sums across teams, it converts to money in one multiplication, and its coarseness keeps the conversation honest.

Do not use them inside a sprint. Task-level work is better served by whatever relative sizing the team already calibrates against its own history — the units answer different questions, and neither replaces the other.

[The essay behind “FTE-month” →](https://www.deliverysheet.com/blog/fte-months-capacity-unit) [Topic: Capacity and what to measure →](https://www.deliverysheet.com/topics/capacity)

## **Related terms **

- [Allocation vs consumption](https://www.deliverysheet.com/glossary/allocation-vs-consumption)

  Allocation is what people are committed to; consumption is what they spent. Delivery governance measures allocation and deliberately does not measure consumption.
- [Capacity planning](https://www.deliverysheet.com/glossary/capacity-planning)

  Capacity planning establishes what each team can honestly promise for a period — gross FTE-months minus what is already spoken for — and commits demands against that line in priority order.
- [Capacity line](https://www.deliverysheet.com/glossary/capacity-line)

  A capacity line is a team's honestly available capacity for a period, stated in FTE-months — the constraint that commitments are walked down against, in priority order, until it is spent.

This definition comes from building **DeliverySheet** — it takes a vague work request to a clear delivery decision, so the shape, owner, capacity, dependencies and open questions are on the table before anyone commits people or a date.

$189/month per workspace, unlimited members. 7-day free trial — card required, cancel before it ends and you're not charged. I answer the support email myself.

[**Start 7-day trial **](https://www.deliverysheet.com/login?next=/app) [**All terms **](https://www.deliverysheet.com/glossary) [**See pricing **](https://www.deliverysheet.com/pricing)

```json
{"@context":"https://schema.org","@type":"DefinedTerm","@id":"https://www.deliverysheet.com/glossary/fte-month#term","name":"FTE-month","description":"An FTE-month is one full-time person working for one month — a capacity unit that is comparable across teams and, where cost is recorded, is the multiplier a cost forecast would use.","url":"https://www.deliverysheet.com/glossary/fte-month","inDefinedTermSet":"https://www.deliverysheet.com/glossary#termset"}
```

```json
{"@context":"https://schema.org","@graph":[{"@id":"https://www.deliverysheet.com/#website","@type":"WebSite","description":"Turn raw work requests into structured, decision-ready demands before you commit people, budget, or a date. AI-assisted shaping, planning and commitment governance for engineering leaders.","name":"DeliverySheet","url":"https://www.deliverysheet.com/","publisher":{"@id":"https://www.deliverysheet.com/#identity"}},{"@id":"https://www.deliverysheet.com/glossary/fte-month#webpage","description":"An FTE-month is one full-time person working for one month: a coarse capacity unit that sums across teams and converts to cost in one multiplication.","name":"FTE-month — DeliverySheet glossary","url":"https://www.deliverysheet.com/glossary/fte-month","@type":["WebPage","FAQPage"],"breadcrumb":{"@id":"https://www.deliverysheet.com/glossary/fte-month#breadcrumb"},"isPartOf":{"@id":"https://www.deliverysheet.com/#website"},"mainEntity":[{"@id":"https://www.deliverysheet.com/glossary/fte-month#/schema/question/1"}],"potentialAction":[{"@type":"ReadAction","target":["https://www.deliverysheet.com/glossary/fte-month"]}],"primaryImageOfPage":{"@id":"https://www.deliverysheet.com/#logo"}},{"@id":"https://www.deliverysheet.com/#identity","@type":"Organization","alternateName":"Delivery Sheet","description":"Turn raw work requests into structured, decision-ready demands before you commit people, budget, or a date.","name":"DeliverySheet","url":"https://www.deliverysheet.com","founder":{"@type":"Person","@id":"https://www.deliverysheet.com/about#person","name":"Tan Gravam"},"logo":{"@id":"https://www.deliverysheet.com/#logo"}},{"@id":"https://www.deliverysheet.com/glossary/fte-month#breadcrumb","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","name":"Home","item":"https://www.deliverysheet.com","position":1},{"@type":"ListItem","name":"Glossary","item":"https://www.deliverysheet.com/glossary","position":2},{"@type":"ListItem","name":"FTE-month","item":"https://www.deliverysheet.com/glossary/fte-month","position":3}]},{"@id":"https://www.deliverysheet.com/glossary/fte-month#/schema/question/1","@type":"Question","inLanguage":"en","name":"What is an FTE-month?","acceptedAnswer":{"@type":"Answer","text":"An FTE-month is one full-time person working for one month — a capacity unit that is comparable across teams and, where cost is recorded, is the multiplier a cost forecast would use. Unlike story points, which are deliberately team-local and have no monetary meaning, FTE-months can be summed across teams and multiplied by a monthly cost. They are coarse on purpose: the granularity broadcasts its own error bar."}},{"@id":"https://www.deliverysheet.com/#logo","@type":"ImageObject","caption":"DeliverySheet","contentUrl":"https://www.deliverysheet.com/logo.png","inLanguage":"en","url":"https://www.deliverysheet.com/logo.png"}]}
```

## Sitemap

See the full [sitemap](https://www.deliverysheet.com/sitemap.md) for all pages.