What is an FTE-month?

One full-time person working for one month — a capacity unit that is comparable across teams and, where cost is recorded, is the multiplier a cost forecast would use.

Unlike story points, which are deliberately team-local and have no monetary meaning, FTE-months can be summed across teams and multiplied by a monthly cost. They are coarse on purpose: the granularity broadcasts its own error bar.

How to calculate FTE-months

Gross capacity first: headcount multiplied by the months in the period. A team of six over a quarter has 6 × 3 = 18 FTE-months. Then subtract what is already spoken for — the support rotation, run-the-business work, booked holidays, the standing meeting load — and an interruption reserve if you have no data yet (twenty per cent is a defensible opening claim). What remains is the honest line: the capacity that can actually be promised.

Sizing a demand works in the same unit: two people for two months is 4 FTE-months, whichever two people it turns out to be. One decimal place at most — an FTE-month estimate with two significant figures is claiming a precision the unit deliberately does not have.

When to use FTE-months — and when not to

Use them at the altitude where a promise is being made to someone outside the team: commitment decisions, quarter plans, budget conversations. That is where the unit's three properties pay: it sums across teams, it converts to money in one multiplication, and its coarseness keeps the conversation honest.

Do not use them inside a sprint. Task-level work is better served by whatever relative sizing the team already calibrates against its own history — the units answer different questions, and neither replaces the other.

Related terms

  • Allocation vs consumption — Allocation is what people are committed to; consumption is what they spent. Delivery governance measures allocation and deliberately does not measure consumption.
  • Capacity planning — Establishing what each team can honestly promise for a period — gross FTE-months minus what is already spoken for — and committing demands against that line in priority order.
  • Capacity line — A team's honestly available capacity for a period, stated in FTE-months — the constraint that commitments are walked down against, in priority order, until it is spent.